Owners of Pepeekeo power plant site seek dismissal from lien

Subscribe Now Choose a package that suits your preferences.
Start Free Account Get access to 7 premium stories every month for FREE!
Already a Subscriber? Current print subscriber? Activate your complimentary Digital account.

The owners of a 25-acre Pepeekeo site of an electrical power plant under construction are looking to be dismissed from a $35 million mechanic’s lien filed by the former construction contractor.

The owners of a 25-acre Pepeekeo site of an electrical power plant under construction are looking to be dismissed from a $35 million mechanic’s lien filed by the former construction contractor.

On Wednesday, 3rd Circuit Judge Glenn Hara took a motion for summary judgment by Maukaloa Farms LLC against Hawaiian Dredging Construction Co. under advisement. Maukaloa, the property owner, is named in the lien application by Hawaiian Dredging, which claims lessee Hu Honua Bioenergy LLC owes $35 million in unpaid construction bills. Hawaiian Dredging withdrew from the site in January, and Hu Honua announced in February that Performance Mechanical Inc. is the new contractor.

Jessie Schiel, Maukaloa’s attorney, argued under Hawaii law the lessor is not responsible for unpaid bills by the lessee unless the lease requires the improvements — in this case the construction of the plant, which, if completed, would burn wood chips to generate 21.5 megawatts of electricity.

“There is no provision that requires Hu Honua to construct a power plant,” Schiel told the judge. “The lienor is relying on the lease provision that (the property) be used for a power plant, but it can be used by any other use permitted by law. … Any use permitted by law includes 62 other permitted uses in the industrial district, any of which … are permissible per this law.”

“Moreover, the construction taking place on this property by the lessee, Hu Honua, the lease is very clear,” Schiel continued. “No improvements over $500,000 without prior approval of the contractor by the lessor, prior approval of the plan by the lessor, a (construction) bond. … None of those pre-construction requirements occurred.”

Schiel described a clause in the lease stating the land is to be used for operating an electrical power plant and selling energy as “a boilerplate provision in any lease of this sort.”

“It’s a standard provision. It does not require the lessee to undertake the improvements,” he said.

Schiel added that Maukaloa notified Hu Honua in July it had breached the lease and noted Maukaloa has a pending lawsuit against the bioenergy company.

Keith Yamada, one of two lawyers representing Hawaiian Dredging, argued Maukaloa is liable for Hu Honua’s alleged delinquent bills because the lease requires the power plant be built.

“I’ll just read the clause,” he said. “‘Lessee shall use the land only for the business of … operating an electric energy generation power plant and selling energy generated therefrom to HELCO or some other purchaser and’ — not or, and — ‘other uses incidental thereto and’ — another and, not an or, and — ‘any other use permitted by law.’”

“It’s not only a permitted use … but it’s a mandatory use, because it says here ‘lessee shall use the land only for the business of operating an electric energy generation power plant,’” Yamada continued.

“Isn’t the import of that whole section saying you will not violate the facility ordinance by having something unpermitted on the property?” Hara asked.

“Well, that’s part of it, but it’s also requiring an electric energy generation power plant. It says that. You have to do that. … There’s other provisions in this lease that specifically point to the fact that an electric energy power plant is going to be operated on these premises,” Yamada replied.

“But isn’t there a plant already there?” the judge inquired.

“There is, but it’s not a biomass-to-energy power plant. It hasn’t been used for years,” Yamada said.

The site is the former Hilo Coast Processing Co. electrical power plant that at one time burned bagasse, a sugarcane byproduct. The plant was later converted to burn coal.

Hu Honua’s attorney, Blake Bushnell, said his client “is in support of the motion for summary judgment” in Maukaloa’s favor.

A probable cause hearing on Hawaiian Dredging’s lien application is scheduled for 9 a.m. July 30 before 3rd Circuit Judge Greg Nakamura. There are also a number of smaller lien requests filed against Hu Honua by project subcontractors and suppliers.

Email John Burnett at jburnett@hawaiitribune-herald.com.